The commissioning phase includes taking the charging equipment into use, such as powering, configuring and testing the equipment. For additional information, see the user manual.
Qualifications
We recommend that you have an authorized electrician on site during commissioning to repair possible electrical installation errors.
General requirements
Obey Kempower commissioning instructions. For additional information, see the user manual.
Use the Kempower Commissioning Tool software (or Kempower Maintenance Tool for offline cases) to configure the charging equipment.
Testing
Note
Note that this is an indicative list, not a comprehensive checklist for testing your charging site.
Test the cloud connection to the third-party backend system (option). Also test the second SIM card (nano) and wireless connection, if applicable.
Test each charging output using either a suitable electric vehicle or a Comemso EV simulator/charger tester (min. 1 minute/vehicle connector).
Test the equipment stop function (option).
Inspection
Complete the commissioning according to the Kempower commissioning checklist. Submit the completed document to Kempower ChargEye. For additional information, contact Kempower Technical Support.