Installation requirements

Power Unit owner's manual

The installation phase includes both the mechanical and electrical installation of the charging equipment. For additional information, see the user manual.

Qualifications

General requirements

  • Obey local rules and requirements on civil works, electrical installations, cable routing, cable dimensioning, and health and safety, such as local regulations regarding personal protective equipment (PPE).

  • Obey Kempower installation instructions. For additional information, see the user manual.

  • Submit site plans for sites with more than 250 kW of charging capacity and five or more charging outputs to be reviewed and approved by Kempower Solutions Support before you start the installation.

  • Use suitable tools and equipment for the installation. For additional information, see the Kempower certification training materials and the user manual.

  • Before you start the installation, make sure that all delivered parts are correct and not damaged.

Testing

Note

Note that this is an indicative list, not a comprehensive checklist for testing your charging site.

  • Test the installation for electrical safety (usually done by an external electrical inspector). Obey local rules and requirements.

  • Examine and correctly set the AC main supply circuit breaker current for each Power Unit.

  • Do the following electrical tests:

    • Ethernet cables tests (such as correct cable type, correct wiring, attenuation).

    • Continuity tests for power and control cables and the protective circuit.

    • Other tests required by local rules and regulations.

Inspection

Inspect the installation according to the Kempower installation checklist. Submit the completed document to Kempower ChargEye. For additional information, contact Kempower Technical Support.